By Jeff Bell.
It is common practice at the end of a major project to work through a “lessons learned” exercise.
The intent is to capture what we did well and what could have been improved, so next time we will achieve an even better outcome.
OK, so it’s not as common practice as it should be. Alright, it almost never happens.
I assume (a dangerous practice in itself) that the thinking is: “It’s done now, there’s nothing that we can do to change the outcome.” Which may be true, but is shortsighted.
As uncomfortable as it is to look back, it is invariably useful. But it’s not an exercise of pin the blame on the donkey. It should aim to be overwhelmingly positive, without being Pollyanna. A useful structure, “owned” by an independent reviewer of the project is:
- Devise an attendance list and issue invitations—all the key stakeholders (including the customer) in the project. Make sure timing is convenient to all and attach an agenda. Allow 2-4 hours.
- Review the original agreement / brief / plan.
- Present the actual outcomes.
- Assess the significant differences (with their reasons) and the consistencies.
- Openly discuss, with a “no personal attacks by anyone” brief.
- Document the actions: more of, the same, less of. Ensure that each action has a person responsible for completion and a due by date.
- Soon after the meeting, devise a summary and distribute to all stakeholders for final checking.
- Publish.
We can call this the postmortem, though hopefully there is no cadaver.
Now, if you think this process will shift us out of our comfort zone, that’s great, because our best learning happens in at least mild discomfort.
And here is something that is likely to shift you further, but on this occasion, it is looking forward: the premortem.
It was devised by research psychologist Gary Klein and I first saw it referred to in Daniel Kahneman’s Thinking, Fast and Slow, the best book I have ever read about the psychology of decision-making.
The premortem is a powerful tool to use in the face of uncritical optimism, which is how most projects gain their impetus. It comes just before the organisation makes a binding commitment to the project:
Imagine that you are one year beyond the completion of this major project—and it has been a disaster. Take 10min. to write a brief history of that disaster.
Personally, I would allow 30min. for this writing exercise, because we would like the participants to pick the eyes out of the plan and expected outcomes, all the while concentrating on what could go wrong. This “right to left” technique mirrors what happens in re-engineering methodology where we seek to redesign the means to achieve the best outcome.
Klein designed the challenge to overcome groupthink (everyone seeking harmony at the expense of a rigorous outcome) and to unleash the imagination of the key participants. At this advanced planning stage, many people feel that they are under pressure to align and that anything that looks like doubt is an act of disloyalty—threatening their own participation, or even the project.
In last week’s post, I attempted to highlight the dangers of optimism bias—whereby it could lead not only to poor decisions, but a failure to see and learn from the consequences.
The premortem presents an opportunity to give vent to doubts and to legitimize them—raising the possibility of either a more robust plan of action or, at the extreme, abandonment of a too risky project.
I am talking here about engaging Kahneman’s System 2 thinking—mature, considered, wide-ranging—in the pursuit of better decision-making. As much as it threatens to dull the glow of a new “romance” this can save the players from a heavy fall.
It is at this time, before taking the plunge, that most starry-eyed predictions of success are expressed. Possibly to cover up the feeling that we are at the point of no return—where we may even call on that old chestnut “I feel this is right, I have an intuition.”
Knowing that, as Herbert Simon said:
“Intuition is nothing more and nothing less than recognition.”